Saturday 16th November 2024

The Marshalltown City Council was faced with two change orders for work at the Marshalltown Airport, which according to the original contract, should have been completed by now. The general contractor, Garling construction requested a time extension and additional funds to cover administrative costs. Due to supply chain issues, the 3-month extension was granted, but the Council did not approve an additional $28,000 for added costs.

The Council also discussed entering into a partnership with Marshalltown Company to combat flooding issues on South 8th street as the company continues to expand.